H. P. Bruns - 6 - April 8, 1970
Actual Expenditures J anuary February March
Man-Hours ST - Dept. 4190 959 840
Man-Hours ST - Purchased 11 0
Man-Hours OT ■- Dept. 4190 441 548.5
Man-Hours OT - Purchased 18 0
Total Man-Hours 1,429 1,137 1,388.5
Man-Hour Cost 9,281.47 7,010.41 8,645.86
Burden 5,542.30 5,770.87 5,735.50
Travel 1,753.84 2,068.02 1,925.96
Material 2,358.11 3,169.21 2,930.75
Material Committed (not billed)
Overtime Prem. 1,505.15 740.34 1,052.36
Relocation 995.3^ 102.15
Markup 2,808.14 2,457.41 2,671.43
Total Cost 24,244.35 21,216.26 23,064.01
Billing Act.** 24,244.35 21,216.26 23,064.01