III. Operation Plan
A. Separate Burden Center:
. CHO will staff the Operation Center with off-site operating personnel
and collect costs under a separate Plant 7804 Burden Center.
B. Staffing:
CHO will staff the operation initially with the following types of
personnel:
(1) Code 19 Supervisor
(2) Code 20 Senior Engineers
(1) Code 25 Engineer B
(3) Code 25 Project Technicians
(1) Code 27 Field Technician General
C. Facilities and Equipment:
The Chrysler Engineering Office-Highland Park will lease the basic
facility and provide a suitable working area for vehicle operation.
Equipment, tools, and supplies required for operation and maintenance
will be purchased or transferred from the Chrysler-Detroit Woodward Garage function.
D. Support Services:
Additional specialized services will be purchased from CHO or local
sources as required to include:
1. Engineering (Mechanical and Electrical)
2. Fabrication (Electrical and Sheet-metal)
3. Machine Shop